The Assignment

Offshore facilities present demanding reality-capture conditions due to their remote locations, complex industrial infrastructure and tightly controlled access. Capturing these environments requires detailed planning and efficient field execution within limited access windows.

The assignment involved carrying out high-detail terrestrial laser scanning across remote offshore facilities, creating comprehensive digital capture of complex existing conditions while working within strict site-access and operational constraints.

Our Approach

CS TECH Ai's North American reality-capture team deployed a focused four-person field team to execute the offshore scanning programme within a tightly managed schedule.

The engagement included:

  • Terrestrial laser scanning of complex offshore facilities
  • High-detail capture of existing industrial infrastructure and equipment
  • Planning of scan positions to provide comprehensive coverage across complex environments
  • Capture within strict site-access and operational constraints
  • Field coordination around restricted working windows
  • Systematic collection of approximately 3,000 individual scans
  • Management and organization of large volumes of captured spatial data
  • Quality-focused field execution to minimise the need for repeat capture
  • Completion of the scanning programme within 17 days

The compact field team and structured capture approach enabled a substantial volume of reality-capture data to be collected within the available offshore access window.

Impact

Completed approximately 3,000 terrestrial laser scans across the offshore facilities.
Executed the field programme in just 17 days.
Delivered the scanning programme using a focused 4-person team.
Captured detailed existing conditions across complex industrial environments.
Worked effectively within the logistical and access constraints associated with remote offshore facilities.
Created a comprehensive digital record to support subsequent engineering and project requirements.